ANALISIS KEHANDALAN DAN RISK BASED INSPECTION PADA HEAT RECOVERY BOILER PSEL DENGAN METODE FAILURE MODE AND EFFECTS ANALYSIS (FMEA) DAN FISHBONE DIAGRAM

*Arkan Bimo Alkautsar  -  Department of Mechanical Engineering, Universitas Diponegoro, Jl. Prof. Sudarto, SH, Tembalang, Semarang, Indonesia 50275, Indonesia
Gunawan Dwi Haryadi  -  Department of Mechanical Engineering, Universitas Diponegoro, Jl. Prof. Sudarto, SH, Tembalang, Semarang, Indonesia 50275, Indonesia
Yusuf Umardani  -  Department of Mechanical Engineering, Universitas Diponegoro, Jl. Prof. Sudarto, SH, Tembalang, Semarang, Indonesia 50275, Indonesia

Citation Format:
Abstract

Heat Recovery Boiler (HRB) merupakan salah satu komponen utama pada sistem Pembangkit Listrik Tenaga Sampah (PSEL) yang berfungsi memanfaatkan energi panas hasil proses pembakaran sampah menjadi energi uap untuk menggerakkan turbin dan generator dalam menghasilkan listrik. Keandalan Heat Recovery Boiler sangat menentukan kontinuitas operasi pembangkit karena komponen ini bekerja pada temperatur dan tekanan tinggi serta terpapar gas hasil pembakaran yang mengandung senyawa korosif. Kondisi tersebut menyebabkan komponen boiler rentan mengalami kerusakan, seperti korosi, erosi, penipisan dinding pipa, kebocoran, maupun kegagalan material yang dapat mengakibatkan penurunan efisiensi hingga terjadinya unplanned shutdown. Oleh karena itu, diperlukan strategi pemeliharaan dan inspeksi yang mampu mengidentifikasi serta memprioritaskan risiko kegagalan secara sistematis. Penelitian ini bertujuan mengidentifikasi komponen kritis pada Heat Recovery Boiler, menganalisis tingkat risiko kegagalan menggunakan metode Failure Mode and Effects Analysis (FMEA), mengidentifikasi akar penyebab kegagalan melalui Fishbone Diagram, serta menyusun strategi inspeksi berbasis risiko menggunakan metode Risk-Based Inspection (RBI). Hasil analisis Failure Mode and Effects Analysis (FMEA) menunjukkan bahwa komponen Water Wall Tube memiliki nilai Risk Priority Number (RPN) tertinggi sehingga ditetapkan sebagai komponen dengan tingkat prioritas risiko paling tinggi. Analisis Fishbone Diagram menunjukkan bahwa penyebab kegagalan dipengaruhi oleh faktor manusia, mesin, metode, material, pengukuran, dan lingkungan yang saling berkaitan. Selanjutnya, penerapan Risk-Based Inspection (RBI) mengelompokkan komponen berdasarkan tingkat risiko sehingga dapat digunakan sebagai dasar dalam menentukan prioritas inspeksi, metode inspeksi yang sesuai, serta frekuensi inspeksi yang optimal. Penerapan pendekatan Failure Mode and Effects Analysis (FMEA), Fishbone Diagram, dan Risk-Based Inspection (RBI) diharapkan mampu meningkatkan keandalan Heat Recovery Boiler, meminimalkan potensi kegagalan, mengurangi risiko unplanned shutdown, serta mendukung keberlangsungan operasi PSEL secara aman, efektif, dan efisien.

Keywords: heat recovery boiler; risiko kegagalan
Article Info
  1. Tan, H., Wang, C., & Chen, G. (2020). Waste-to-Energy Incineration Technologies and Heat Recovery Systems. Renewable and Sustainable Energy Reviews, 119, 109589
  2. Liu, Y., Zhang, X., & Li, J. (2020). Performance Analysis of Waste Heat Recovery Boiler in Municipal Solid Waste Incineration Power Plants. Energy Reports, 6, 1318–1327
  3. Zhang, L., Wang, H., & Zhao, Y. (2021). High-Temperature Corrosion Characteristics of Boiler Tubes in Municipal Solid Waste Incineration Plants. Engineering Failure Analysis, 124, 105363
  4. Stamatis, D. H. (2003). Failure Mode and Effect Analysis: FMEA from Theory to Execution. 2nd ed. Milwaukee: ASQ Quality Press
  5. American Petroleum Institute. (2016). API Recommended Practice 580: Risk-Based Inspection. 3rd ed. Washington, DC: American Petroleum Institute
  6. IEC. IEC 60812: Failure Modes and Effects Analysis (FMEA and FMECA). Geneva: International Electrotechnical Commission, 2018
  7. ASM International. ASM Handbook, Volume 11: Failure Analysis and Prevention. Materials Park, OH: ASM International, 2002
  8. Ishikawa, K. Introduction to Quality Control. Tokyo: 3A Corporation, 1990
  9. American Petroleum Institute. API Recommended Practice 581: Risk-Based Inspection Methodology. 3rd ed. Washington, DC: American Petroleum Institute, 2016
  10. Tan, H., Wang, C., & Chen, G. (2020). Waste-to-Energy Incineration Technologies and Heat Recovery Systems. Renewable and Sustainable Energy Reviews, 119, 109589
  11. Liu, Y., Zhang, X., & Li, J. (2020). Performance Analysis of Waste Heat Recovery Boiler in Municipal Solid Waste Incineration Power Plants. Energy Reports, 6, 1318–1327
  12. Babcock & Wilcox. (2018). Steam: Its Generation and Use. 42nd ed. Barberton, OH: Babcock & Wilcox
  13. Zhang, L., Wang, H., & Zhao, Y. (2021). High-Temperature Corrosion Characteristics of Boiler Tubes in Municipal Solid Waste Incineration Plants. Engineering Failure Analysis, 124, 105363
  14. ASM International. ASM Handbook, Volume 11: Failure Analysis and Prevention. Materials Park, OH: ASM International, 2002
  15. Viswanathan, R. Damage Mechanisms and Life Assessment of High-Temperature Components. Materials Park, OH: ASM International, 2008
  16. Stamatis, D. H. Failure Mode and Effect Analysis: FMEA from Theory to Execution. 2nd ed. Milwaukee: ASQ Quality Press, 2003.
  17. D. A. Tillman, Steam Generation and Waste Heat Recovery Systems. Tulsa, OK, USA: PennWell Corporation, 2013
  18. T. A. Adams and P. I. Barton, "Reliability and Maintenance Optimization of Industrial Boiler Systems," Applied Thermal Engineering, vol. 115, pp. 1145–1156, 2017
  19. API Recommended Practice 581, Risk-Based Inspection Methodology, 3rd ed. Washington, DC, USA: American Petroleum Institute, 2016
  20. IEC 60812, Failure Modes and Effects Analysis (FMEA and FMECA), International Electrotechnical Commission, Geneva, Switzerland, 2018
  21. K. Ishikawa, Introduction to Quality Control. Tokyo, Japan: 3A Corporation, 1986
  22. ASM International, Failure Analysis and Prevention, ASM Handbook, vol. 11. Materials Park, OH, USA: ASM International, 2002
  23. American Petroleum Institute. API Recommended Practice 580: Risk-Based Inspection. 3rd ed. Washington, DC: American Petroleum Institute, 2016
  24. American Petroleum Institute. API Recommended Practice 581: Risk-Based Inspection Methodology. 3rd ed. Washington, DC: American Petroleum Institute, 2016